8330 N RESEDA BLVD 91324
APPLICATION / PERMIT NUMBER: 16014-20000-06312
PLAN CHECK / JOB NUMBER: B16VN18273

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-Addition
SUB-TYPE: Commercial
PRIMARY USE: (13) Medical Office
WORK DESCRIPTION: ADD 39'-3" X 65'-9" TWO STORY ADMINISTRATIVE OFFICES TO THE REAR OF (E) TWO STORY MEDICAL OFFICE & PARTIALLY RE-STRIPE OPEN PARKING LOT - SEE COMMENTS
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 01/31/2018 ISSUING OFFICE: Van Nuys
CURRENT STATUS: CofO Issued CURRENT STATUS DATE: 02/20/2019

Permit Application Status History
Submitted 12/30/2016 APPLICANT
Green Plans Picked Up 02/09/2017 APPLICANT
Disabled Access Plans Picked Up 02/15/2017 APPLICANT
Assigned to Plan Check Engineer 02/23/2017 MOURAD AZIZ
Corrections Issued 02/27/2017 MOURAD AZIZ
Quality Review Completed 03/03/2017 GUANG MIN TUNG
Building Plans Picked Up 03/06/2017 APPLICANT
Applicant returned to address corrections 07/25/2017 MOURAD AZIZ
Applicant returned to address corrections 08/16/2017 MOURAD AZIZ
Applicant returned to address corrections 08/22/2017 MOURAD AZIZ
Plan Check Approved 09/22/2017 MOURAD AZIZ
Issued 01/31/2018 LADBS
CofO in Progress 02/19/2019 ANDREW DORSO
Permit Finaled 02/20/2019 JAMES STEPHENS
CofO Issued 02/20/2019 JAMES STEPHENS
Permit Finaled 02/20/2019 JAMES STEPHENS

Permit Application Clearance Information
Hydrant and Access approval Cleared 03/21/2017 JOHN DALLAS
Miscellaneous Cleared 07/21/2017 DANIEL SKOLNICK
ZA Case Cleared 07/21/2017 DANIEL SKOLNICK
Prkng lot landscape/Water mgmt Cleared 08/03/2017 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 08/08/2017 LEE GUILBEAUX
Sewer availability Cleared 08/08/2017 LEE GUILBEAUX
DAS Clearance Cleared 08/16/2017 MOURAD AZIZ
Green Code Cleared 09/11/2017 MICKEY YAMASHITA
Highway dedication Cleared 09/11/2017 CHRISTOPHER TOMES
Low Impact Development Cleared 09/20/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 09/20/2017 RAVIL MANAPOV

Licensed Professional/Contractor Information
Architect Information
Harte, Monika Hanna; Lic. No.: C19348
23147 VENTURA BLVD SUITE 200
WOODLAND HILLS, CA  91364
Contractor Information
Butland E H Corp; Lic. No.: 831933-B
6100 YOLANDA AVENUE
RESEDA, CA  91335
Engineer Information
Husain, Shahzain; Lic. No.: C62744
1710 N MOORPARK RD #100
THOUSAND OAKS, CA  91360

Inspection Activity Information

Inspector Information
DEANDRE HOFFMAN, (818) 374-1105
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Footing/Foundation/Slab   04/26/2018   Partial Approval   ROBERT DAVIS
  Footing/Foundation/Slab   05/03/2018   Partial Approval   DANNY RODRIGUEZ
  Deputy Reinf. Concrete   05/04/2018   Conditional Approval   JAMES STEPHENS
  Deputy Drilled-In Anchors   05/14/2018   Partial Approval   DANIEL VARNUM
  Footing/Foundation/Slab   05/16/2018   Partial Inspection   ANDREW DORSO
  Deputy Reinf. Concrete   05/17/2018   Conditional Approval   JAMES STEPHENS
  Drywall Nailing   05/29/2018   Partial Approval   JEFFREY DURAN
  Drywall Nailing   06/05/2018   Partial Inspection   ANDREW DORSO
  Floor/Roof Diaphrgm/Shear Wall   06/05/2018   Partial Inspection   ANDREW DORSO
  Green Building Rough   06/05/2018   Not Ready for Inspection   ANDREW DORSO
  Drywall Nailing   06/12/2018   Partial Approval   DANIEL VARNUM
  Green Building Rough   06/22/2018   Not Ready for Inspection   JEFFREY DURAN
  Wood Frame   06/22/2018   Conditional Approval   JEFFREY DURAN
  Drywall Nailing   06/25/2018   Partial Approval   JEFFREY DURAN
  Deputy Drilled-In Anchors   06/28/2018   Approved   JEFFREY DURAN
  Deputy Wood Construction   06/28/2018   Approved   JEFFREY DURAN
  Green Building Rough   06/28/2018   Not Ready for Inspection   JEFFREY DURAN
  Insulation   06/28/2018   Partial Approval   JEFFREY DURAN
  Wood Frame   06/28/2018   Partial Approval   JEFFREY DURAN
  Green Building Rough   07/02/2018   Not Ready for Inspection   DANIEL VARNUM
  Wood Frame   07/02/2018   Partial Inspection   DANIEL VARNUM
  Interior/Exterior Lathing   07/09/2018   Approved   DANIEL VARNUM
  Insulation   07/16/2018   Not Ready for Inspection   ANDREW DORSO
  Insulation   07/24/2018   Approved   JEFFREY DURAN
  Drywall Nailing   07/25/2018   Not Ready for Inspection   DANIEL MC AULIFFE
  Insulation   07/26/2018   Partial Approval   DANNY RODRIGUEZ
  Drywall Nailing   07/27/2018   Partial Approval   CAMERON CHABAN
  Drywall Nailing   08/01/2018   Partial Inspection   ANDREW DORSO
  Drywall Nailing   08/06/2018   Partial Approval   JEFFREY DURAN
  Insulation   08/06/2018   Partial Approval   JEFFREY DURAN
  Drywall Nailing   08/10/2018   Partial Inspection   ANDREW DORSO
  Drywall Nailing   08/17/2018   Partial Inspection   ANDREW DORSO
  Green Building Rough   09/24/2018   Not Ready for Inspection   CAMERON CHABAN
  Deputy Drilled-In Anchors   10/29/2018   Conditional Approval   CAMERON CHABAN
  T-Bar Ceiling   11/05/2018   Not Ready for Inspection   JEFFREY DURAN
  Deputy Drilled-In Anchors   11/08/2018   Conditional Approval   JAMES STEPHENS
  Footing/Foundation/Slab   11/09/2018   Not Ready for Inspection   DANNY RODRIGUEZ
  Footing/Foundation/Slab   11/14/2018   Conditional Approval   CAMERON CHABAN
  Green Building Rough   11/14/2018   Not Ready for Inspection   CAMERON CHABAN
  T-Bar Ceiling   11/15/2018   Approved   DANIEL VARNUM
  Deputy Drilled-In Anchors   11/16/2018   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   11/16/2018   Conditional Approval   CAMERON CHABAN
  Deputy Steel/Welding   11/26/2018   Conditional Approval   CAMERON CHABAN
  Deputy Wood Construction   11/27/2018   Conditional Approval   DANIEL VARNUM
  Green Building Rough   12/04/2018   Not Ready for Inspection   DANIEL VARNUM
  Light Gage Steel Frame   12/04/2018   Approved   DANIEL VARNUM
  Wood Frame   12/04/2018   Partial Approval   DANIEL VARNUM
  Drywall Nailing   12/07/2018   Partial Approval   DANIEL VARNUM
  Deputy Drilled-In Anchors   12/24/2018   Conditional Approval   DANIEL VARNUM
  T-Bar Ceiling   12/27/2018   Not Ready for Inspection   JEFFREY DURAN
  T-Bar Ceiling   12/31/2018   Approved   DANIEL VARNUM
  Green Building Final   01/02/2019   Not Ready for Inspection   DANIEL VARNUM
  Final   02/06/2019   Corrections Issued   ANDREW DORSO
  Footing/Foundation/Slab   02/06/2019   Partial Approval   ANDREW DORSO
  Green Building Final   02/06/2019   Approved   ANDREW DORSO
  Green Building Rough   02/06/2019   Approved   ANDREW DORSO
  SGSOV-Seismic Gas S/O Valve   02/06/2019   SGSOV Approved   ANDREW DORSO
  Smoke Detectors   02/06/2019   Approved   ANDREW DORSO
  Wood Frame   02/06/2019   Partial Approval   ANDREW DORSO
  Final   02/19/2019   OK to Issue CofO   ANDREW DORSO
  Footing/Foundation/Slab   02/19/2019   Approved   ANDREW DORSO
  Wood Frame   02/19/2019   Approved   ANDREW DORSO